首页 体育内容详情
以太坊开奖网(www.326681.com)_Kota Baru-Kuala Krai highway project\u00a0faces 308-day delay

以太坊开奖网(www.326681.com)_Kota Baru-Kuala Krai highway project\u00a0faces 308-day delay

分类:体育

网址:

SEO查询: 爱站网 站长工具

点击直达

以太坊开奖网www.326681.com)采用以太坊区块链高度哈希值作为统计数据,以太坊开奖网(联博统计)数据开源、公平、无任何作弊可能性。联博统计免费提供API接口,支持多语言接入

,Economy Minister Mustapa Mohamed says the Kota Baru-Kuala Krai highway is expected to be completed by 2025. – The Malaysian Insight file pic, June 14, 2022.

THE Kota Baru-Kuala Krai highway Package 2B – a 6.2km stretch from Ketereh to Kok Lanas – was supposed to be completed a month ago but is now facing a 308-day (23%) delay.

Economy Minister Mustapa Mohamed said the highway project, which involves seven packages with a total estimated cost of RM2.7 billion, is expected to be completed by 2025.

Two packages are completed, while five others are in the construction phase, he added.

“Packages 2C and 3A Kok Lanas-Bukit Tiu (19.13km), 3B Kampung Berangan Mek Nab-Keroh (9.78km) and 3C Keroh-Kuala Krai (8.6km) are proceeding according to schedule.

“The Kelantan Public Works Department is taking steps to overcome the delay and prepare the project, including dismissing the contractor involved.”

Mustapa said expansion and upgrading works are also met with a delay at Sultan Ismail Petra Airport in Pengkalan Chepa, which is another “sick project”.

“The main issues behind the 100-day delay are manpower shortage, rise in construction costs and unsatisfactory contractor performance.” – Bernama, June 14, 2022.


转载说明:本文转载自Sunbet。
  • 收购usdt(www.usdt8.vip) @回复Ta

    2022-07-31 00:12:36 

    Bank Islam Malaysia Bhd chief economist Mohd Afzanizam Abdul Rashid said, however, the greenback remains stable as the US Dollar Index (DXY) continues to hover above 107 points.以前怎么没看到这个

发布评论